Bayfield Shared Use Path Improvements Project

Invitation to Bid

Separate sealed BIDS for the construction of the Bayfield Shared Use Path Improvements Project will be received at Bayfield Town Hall, 1199 Bayfield Parkway, Bayfield, CO 81122. until 2:00pm (Town’s Clock), on March 25, 2024, at which time they will be publicly opened and read aloud. No determination of award will be made at that time.

This project removes existing 10 ft wide x 4475 ft. long asphalt surfaced shared use path and replaces it with new 10 ft wide x 6” thick concrete surfacing and detectable warnings. Project includes stormwater management, erosion control, and traffic control.

Traffic control will be the responsibility of the contractor. Traffic control plans will be required for submittal and approval. The contractor will be required to submit a phasing plan and work with the Town and the Owner’s Representative (OR) to determine a plan with the least impact to businesses in the project area. Access to businesses shall remain open for the duration of the project. Public Notification will be handled by the Town of Bayfield, but the awarded contractor should expect to be present in meetings with business owners to communicate the phasing plan prior to beginning work and shall meet weekly to update the OR of the proposed work for that week.

Contractor shall be responsible to obtain and manage a Stormwater Permit for Construction Related Discharges through Colorado Department of Public Health and Environment.

The Town of Bayfield may award a contract to the lowest responsible bid, based on the following criteria: (1) The ability, capacity and skill of the bidder to perform the contract or furnish the supplies required; (2) whether the bidder can perform the contract or furnish the supplies promptly or within the time specified, without delay or interference; (3) the character, integrity, reputation, judgment, experience and efficiency of the bidder; (4) the quality of performance on previous contracts. A Bid Bond in the amount of 5% of bid price is required to be submitted with the bid. Performance and Payment Bonds, each in the amount of 100% of bid, will also be required as a condition of issuance of notice to proceed to the successful Bidder. Bid Award and Notice to Proceed will be April 2024. Construction Start date is floating between May 1 and June 1, 2024. Substantial construction completion shall be no later than 90 working days from the Bidder’s selected start date.

A PREFERENCE FOR LOCAL CONTRACTORS WILL NOT BE APPLIED BY THE OWNER WHEN SELECTING A CONTRACTOR.

An optional pre-bid meeting and project walk through will be held at 2:00 pm March 13, 2024, beginning at the Pine River Library located at 395 Bayfield Center Drive, Bayfield, CO 81122.

The Invitation to Bid and any subsequent addenda will be posted to the Rocky Mountain E- Purchasing System website (www.bidnetdirect.com/colorado) then click on Vendor Login or Vendor Registration if you have not already registered. Contractors are encouraged to register with RMEPS for all Town bid opportunities. Bidders wishing to participate should ensure they have all addenda prior to submission of proposals. Failure to acknowledge receipt of any addenda applicable to their project could result in the rejection of a bid.

It is the sole responsibility of the respondent to see that the bid is received before the submission deadline. Late bids will not be considered.

https://www.bayfieldgov.org/rfp-bid-projects